Choose Your Province/State of Service

In order to serve you better, please select your Enbridge Gas location services.

Choose Your Province/State of Service

We noticed you are visiting from Utah, would you like to visit our Utah site?

Continue to Utah's site

Or please select your province/state of your choice so we can display the correct content for your location?

Choose Your Province/State of Service

In order to serve you better, please select your Enbridge Gas location services.

is currently
selected

Go to this state's site Stay on this state's site

Choose Your Province/State of Service

We noticed you are visiting from Utah, would you like to visit our Utah site?

is currently
selected

Enbridge Gas Utah has successfully brought natural gas infrastructure to the towns of Elberta and Goshen in rural Utah, and the project is now in service. With the project in service, approximately 340 homes and businesses can now benefit from reliable natural gas service. This new infrastructure supports both the current needs of the communities and the anticipated future growth of the area.

Make a natural gas service line request

Project Status/timeline

  • Feasibility


  • Environmental studies


  • Regulatory review


  • Regulatory approval


  • Under Construction


  • In-service


Project Status/timeline

  • Feasibility


  • Environmental studies


  • Regulatory review


  • Regulatory approval


  • Under Construction


  • In-service



Project calendar

Timeline Undertakings
May 2018 The allowance of rolling costs into rate base was passed by the Utah Legislature (House Bill 422).
Early 2021 Preliminary routing and environmental studies are underway.
February 2021 Virtual public meetings held & interest forms collected.
March 2021 Request Public Service Commission approval.
October 2021 Preliminary routing and environmental studies are underway.
Q2 2022 Construction to begin
Q4 2022 Project In-Service

Frequently asked questions

Multiple rural communities were surveyed to determine their interest in natural gas. All potential communities were evaluated based on the following criteria:

  • Project cost
  • The number of potential new customers
  • The impact on current Enbridge Gas Utah operations and current infrastructure

Following this evaluation, Enbridge Gas Utah proceeded with extending service to the towns of Elberta and Goshen. The project was completed and is now in service, providing natural gas to approximately 340 homes and businesses. Enbridge Gas anticipated that this new natural gas service would support both the expected and potential growth of the area.

This project was the second to be built under House Bill 422. Following approval by the Utah Public Service Commission, construction began in Q2 2022 and was completed later that year. The project is now in service, with an in-service date in late 2022. It included the installation of approximately 4.5 miles of natural gas pipeline. Preliminary routing was completed prior to construction.

The company views rural expansion under House Bill 422 as an ongoing program with each project subject to Utah Public Service Commission approval.