Enbridge Gas expanded its service to Green River, and the project is now in service. With the extension complete, approximately 450 homes and businesses gained access to natural gas. Enbridge Gas anticipated that the addition of natural gas service would support the area’s expected and potential growth.
Project Status/timeline
-
Feasibility
-
Environmental studies
-
Regulatory review
-
Regulatory approval
-
Under Construction
-
In-service
Project Status/timeline
-
Feasibility
-
Environmental studies
-
Regulatory review
-
Regulatory approval
-
Under Construction
-
In-service
Project calendar
| Proposed timeline | Undertakings |
|---|---|
| May 2018 | The allowance of rolling costs into rate base was passed by the Utah Legislature (House Bill 422). |
| Early 2021 | Preliminary routing and environmental studies are underway. |
| April 2021 | Virtual public meetings held & interest forms collected. |
| Mid 2021 | Commission approval will be required for this project and is expected to be filed during this time; approval to come approximately six months after filing. |
| Early/Mid 2023 | Construction to begin. |
| Late 2023 | Project In-Service. |